Hydraulics
Sanitation and utility networks
Design and supervision of 4.2 km of sanitation collectors and the associated roadworks for an urban extension.
Birtouta · 2021
The network's vertical alignment was optimised to remain fully gravity-fed along its entire length, eliminating a pumping station planned in the preliminary design.
Manholes were positioned according to operational constraints, with access from the final road layout.
The long-term operating savings were presented in a techno-economic report attached to the file.
Key figures
- Length
- 4,2 km
- Manholes
- 96
- Pumping station
- Eliminated
- Duration
- 14 months