Logistics platform — earthworks
Demolition of old buildings and creation of a 1.8-hectare build-ready platform.
Boufarik · 2020
Demolition rubble was crushed on site and reused as sub-base material, reducing truck trips and disposal costs.
Levelling was monitored by differential GPS throughout the earthworks.
Underground networks were laid before final compaction to avoid any subsequent rework.
Key figures
- Area
- 1,8 ha
- Excavation volume
- 34 000 m³
- Material reuse
- 60 %
- Duration
- 7 months